What is a method statement? A plain-English guide with a construction example
What is a method statement? It is a written, step-by-step plan for doing one job safely: the order of work, who does what, the equipment, the controls and what to do if something goes wrong. Clients and main contractors often ask for one before you start, so a clear method statement can get you on site sooner. In the US the same idea is usually called a work plan or job hazard analysis.
I've carried out safety reviews and inspections on offshore installations and onshore oil and gas facilities in many countries, and checking the permit to work or method statement against the job was always part of it. More than once, the work in front of me didn't match the paper. Sometimes conditions had changed on the day; sometimes the equipment being worked on had been modified and nobody had updated the method. Either way, the job stopped until the method was put right.
Want the plan done properly, first time? Our Method Statement Template, $29, takes you through every section a client expects, with a check before each next step, so you can hand it over and get started.
Get the Method Statement Template, $29
Written by Mike Armstrong, a company director of over 30 years. Last reviewed: 20 November 2026.
A method statement is a written plan that sets out, step by step, how one job will be done safely, including the controls from its risk assessment.
Let's leave the oil and gas facilities behind and go somewhere smaller: a three-person groundworks firm, and an email that arrives on a Thursday afternoon.
The main contractor wants the firm to lay a new water pipe across a business park car park on Monday. The email ends: "Please send your RAMS by Friday." The owner reads it twice and asks the room what RAMS stands for. Dave, who has dug more trenches than anyone in the county, puts down his tea. "Risk assessment and method statement," he says. "The risk assessment is what could go wrong. The method statement is how we'll do the job so it doesn't." He writes the steps on the back of a delivery note in ten minutes. The owner types them up, and by Friday lunchtime the RAMS is in the main contractor's inbox. "We've always done it this way," says Dave. "Now it's just written down."
That's the point of this Learn page. A method statement isn't extra paperwork for its own sake; it's the plan a good crew already carries in its head, written down so a client can see it and a new starter can follow it. You'll find out what one is, how it differs from a risk assessment, when the law requires one, what goes in it, a worked example, how to write your own, and where they tend to go wrong.
What is a method statement?
A method statement describes how one job will be done safely, in the order it will be done. The HSE describes a good one as setting out the job in a logical sequence with the controls built in, drawing together the hazards and controls from the risk assessments, and covering what to do if there is serious danger (HSE).
Different countries use different names for the same idea.
| Where | What it's called | Required by law? |
|---|---|---|
| US | A work plan, or a job hazard analysis for a single task | No federal OSHA rule calls for a document named a method statement; OSHA recommends planning the controls for each hazard before work starts (OSHA 3886) |
| UK and Ireland | A method statement | In the UK, only for demolition or dismantling, where the arrangements must be written down before the work begins (CDM 2015, regulation 20) |
| Australia | A safe work method statement (SWMS) | Yes, before any of 18 kinds of high risk construction work starts (Safe Work Australia) |
Whatever the name, a method statement nearly always travels with a risk assessment. So how are the two different?
Method statement vs risk assessment (RAMS)
A risk assessment comes first. It finds what could hurt someone, how badly, and what controls are needed. The method statement comes second: it shows how the job will be done with those controls in place, step by step. Together they are called RAMS, risk assessment and method statement, and many clients and main contractors ask for both before you start.
| Risk assessment | Method statement | |
|---|---|---|
| The question it answers | What could go wrong, and how do we control it? | How will we do this job, safely, from start to finish? |
| What it looks like | A list of hazards, who could be harmed, the risk and the controls | The job in steps, in order, with the people, equipment and checks |
| Is it a legal duty? | In the US, some OSHA standards require one, for example a written hazard assessment where protective equipment is needed (OSHA 1910.132); in the UK, every employer must assess risks, and record them with five or more employees (HSE) | Only in some cases (see the table above) |
| Which comes first? | First | Second, built from the risk assessment |
If you haven't done the risk assessment yet, start there: the Risk Assessment Template finds the hazards and fixes the worst first, and the method statement then shows how the job is done with those fixes in place. In the US, the closest single-task equivalent is the job hazard analysis, which our Job Safety Analysis Template covers.
That's the difference. Next, why construction is where you'll hear about method statements most.
Construction method statements: who asks for them, and the law
A construction method statement is a method statement for a job on a building site, written by the contractor doing the work and usually checked by the client or main contractor (US: general contractor) before work starts.
- In the US, there is no federal requirement for a document called a method statement. OSHA's recommended practices for construction advise planning the controls for each hazard, coordinating with the other employers on site before work starts, and reviewing the job safety analysis with workers before non-routine work (OSHA 3886). Clients and general contractors often ask for a written work plan, which does the same job.
- In the UK, the HSE says method statements are not required by law outside demolition and dismantling, but they are widely used as a practical way to plan, manage and monitor the work. They also tell other contractors on site how the work will affect them, and help the principal contractor build the construction phase plan (HSE). The exception is demolition and dismantling: the arrangements must be recorded in writing before the work begins (CDM 2015, regulation 20).
- In Australia, a safe work method statement must be prepared before high risk construction work starts. It must name the high risk work, its hazards and risks, the controls, and how they will be put in place, monitored and reviewed. If the work departs from it, the work must stop and not restart until it can follow the SWMS (Safe Work Australia, Code of Practice: Construction Work). The 18 kinds of high risk work include a possible fall of more than 2 metres, a trench deeper than 1.5 metres, and work where powered mobile plant is moving (Safe Work Australia).
Outside these three countries, check with your own health and safety regulator. And even where the law is silent, the customer often isn't: no RAMS can mean no start. So what goes in one?
What goes in a method statement
A good method statement covers these parts, in this order:
- The job: what is being done, where, for whom, and what is not included.
- People: who is in charge, who does the work, and the training or licences each needs.
- Before work starts: information from the client, permits, access, barriers and welfare.
- Hazards and controls: from the risk assessment, strongest control first.
- Plant and equipment: what is used, and the checks it needs before use.
- Protective equipment: what must be worn, and when.
- The sequence of work: the steps in order, with a check before each next step.
- Emergency arrangements: first aid, the emergency number, the assembly point and any rescue plan.
- Briefing and sign-off: a record that everyone was briefed, and who authorised the start.
The HSE adds that diagrams often make a method statement clearer, and that checking the work on site against it is a useful way to monitor the job (HSE).
The Method Statement Template ($29, Word) has a section for each of these, a tick list of Australia's 18 kinds of high risk construction work, and a worked example you can copy.
Here's what those parts look like when they are filled in.
Method statement example: a trench for a new water pipe
Back at the groundworks firm, this is the method statement Dave's steps became. The business and names are made up.
| Part | What the example says |
|---|---|
| The job | Dig a trench about 1.2 metres deep and 30 metres long across a business park car park, lay a new water pipe, backfill and reinstate the surface. Resurfacing the whole car park is not included. |
| People | The owner in charge on site; Dave operating the mini excavator; one labourer acting as the banksman (the person who guides the machine). |
| Before work starts | Drawings of underground services from the client; the line of the trench scanned with a cable locator; the work area fenced off; car park users told to use the far entrance. |
| Hazards and controls | Hitting a buried cable or pipe: scan, mark and hand dig near any service. Being struck by the excavator: barriers, banksman, nobody within its reach. Trench collapse: nobody enters until the sides are checked, with trench supports if the ground is poor. Lifting pipes: two-person lift. |
| Plant and equipment | Mini excavator with its daily check done; cable locator; trench supports on site; barriers. |
| Protective equipment | Hard hats, high-visibility clothing, safety boots and gloves at all times. |
| Sequence of work, each with its check | 1. Set up barriers (area clear?) 2. Scan and mark services (all marked?) 3. Dig, hand digging near services (no service hit?) 4. Check the trench sides (stable, or supported?) 5. Lay and join the pipe (joints tested?) 6. Backfill and reinstate (surface level, barriers removed last?) |
| Emergency arrangements | First aid kit in the van; the emergency number; the nearest emergency department; if a service is hit, stop, keep everyone clear and call the utility. |
| Briefing and sign-off | All three sign before the barriers go up; the owner authorises the start. |
Two notes. In Australia, the moving excavator makes this high risk construction work, so this method statement is the job's SWMS. And when the client's drawings turned out to miss a pipe, the crew stopped, updated the method with the new service and briefed everyone again before carrying on: exactly the habit Mike describes at the top of this page.
Want this as a document you can fill in? Start from the Method Statement Template, with the same sections ready to complete.
How to write a method statement in seven steps
These steps follow the HSE's advice on method statements, OSHA's recommended practices for construction, and Safe Work Australia's guidance on SWMS, written for a small business.
1. Do the risk assessment first
Find the hazards, who could be harmed and the controls before you plan the steps. The method statement builds on it, never replaces it.
2. Walk the job with the people who will do it
Go to the site, or talk it through with the crew who will do the work. Safe Work Australia says the person doing the work is usually best placed to prepare the SWMS, with the workers involved. They know the job, and people follow steps they helped write.
3. Write the steps in order, with a check at the end of each
One step per line, in the order the job is done. After each step, write the check that must be passed before the next one starts. Safe Work Australia warns against wording that leaves a decision to the person on the day: be specific.
4. Add the people, equipment and protective equipment
Who is in charge, who does what and with which training; what plant and equipment is used and how it is checked; and what must be worn. Keep protective equipment last in the order of controls, not first.
5. Plan for the bad day
The emergency number, the first aider, the nearest hospital, the assembly point, and a rescue plan for anyone stuck at height, in a confined space or in a trench.
6. Brief the crew and sign it off
Walk everyone through the method before work starts, answer their questions and have them sign. A short toolbox talk is a natural place to do it. Then the person in charge authorises the start. Keep a copy on site, where the crew can see it.
7. Keep it current
When the job changes, the method changes first. If conditions change on the day or the equipment has been modified, stop, update the method, brief the crew again, then carry on. In Australia, that is the law for high risk construction work; everywhere else, it's simply how a good crew works.
Even with those steps, method statements tend to go wrong in the same few ways.
Where method statements go wrong
- Copied from another job. A generic method statement reads well and fits nobody. Safe Work Australia says a generic SWMS must be checked against the actual workplace and changed where needed.
- Written in the office. If the people doing the work never saw it, it describes the job someone imagined, not the one on site.
- Never updated. Conditions change, equipment gets modified, a new crew member arrives. A method statement that stays the same while the job changes is the gap I kept finding on site.
- Filed, not briefed. A method statement nobody has read protects nobody. Brief it, sign it and keep it where the crew can see it.
Put those four right and a method statement becomes what it should be: a plan the client trusts and the crew follows.
Method statements and a safety management system
A method statement is one of the everyday tools of a safety management system, alongside risk assessments, training and toolbox talks. If you run, or plan to run, a health and safety management system to ISO 45001, the standard requires you to plan and control your work, and to keep enough written information to be confident it was done as planned (clause 8.1.1). Its guidance gives procedures and systems of work, and permits to work, as examples. A method statement is one common way to show it for higher-risk jobs. You don't need ISO 45001 to get the value of one today.
What we've covered
A method statement is a written, step-by-step plan for doing one job safely. It follows the risk assessment: the risk assessment decides the controls, the method statement shows how the job is done with them in place, and together they make RAMS. In the UK it is rarely a legal requirement, except for demolition and dismantling; in Australia a SWMS is required for high risk construction work; in the US the same idea is a work plan or job hazard analysis. Write it with the crew, put a check after every step, brief it, and update it the moment the job changes. Dave would tell you the same, over a mug of tea.
What next
- Do the risk assessment first: the Risk Assessment Template finds the hazards and the controls your method statement builds on.
- Write the method statement: the Method Statement Template below gives you every section, ready to fill in.
Method Statement Template (Word), $29. Plan each job step by step, with a check before every next step, a briefing record and an authority to start, so you can show your client the plan and get on site.
Do you need ISO certification?
Has a customer or a tender asked for ISO 9001? We'll get you certified without the wait, the stress or the eye-watering cost.
Method statement FAQ
What is the purpose of a method statement?
To plan a job so it is done safely and the same way by everyone: the steps in order, the controls at each step, who does what and what to do if something goes wrong. It also shows a client or main contractor how you will do the work before they let you start.
What is a method statement in construction?
It is a method statement for a job on a building site: a step-by-step plan from the contractor doing the work, usually asked for by the client or main contractor (US: general contractor) before work starts. In Australia, for high risk construction work, it is called a safe work method statement and is required by law.
Is there a method statement example or sample I can follow?
Yes. The example on this page shows a method statement for digging a trench and laying a water pipe, section by section, and you can use it as a sample for your own job. The Method Statement Template includes a second worked example for work at height.
What does RAMS stand for?
Risk assessment and method statement. The risk assessment finds the hazards and decides the controls; the method statement shows how the job will be done with those controls in place. Many clients and main contractors ask for both before work starts.
What is a method statement in health and safety?
It is a written plan that shows how a job will be done without anyone getting hurt: the hazards and controls from the risk assessment, built into the steps of the job, with the people, equipment and emergency arrangements.
What does a method statement look like?
Usually a few pages: the job details, the people, the checks before work starts, the hazards and controls, the equipment, the steps of the work in order, the emergency arrangements and a sign-off sheet. The worked example on this page shows each part filled in.
About the author
Written by Mike Armstrong, senior ISO consultant, former company director, and founder of Plain Standards. In over 30 years running companies at director level, Mike built his own management systems to drive profit long before he adopted ISO 9001, so he comes at this from the owner's side, not the auditor's. Plain Standards helps small and medium sized businesses get ISO certified.